March 2014 – Part 1
Quite a lot going on this month (now writing in present tense!) As I write this we’re just over halfway through the month. It’s all going on, inside and outside the house. I’ll split March into several blog posts. This post, I’ll split into two sections – inside and outside.
Inside the house
The screed is drying nicely so it’s now ok to walk on. The stud work for the downstairs study, cloakroom and utility has gone up, so we can now get an idea of the final layout of the house. We made a couple of tweaks to one of the sections of stud work, to improve the flow through the house. In the entrance hallway, we were all in agreement to take a corner of the stud work of the cloakroom off. It makes the space a lot more useable, without really sacrificing any space in the cloakroom. I think it’s important to be on site to see these things, as it didn’t seem an issue looking at the plans, but when on site, we mocked up the planned position of the wall, and it just didn’t look right.
Sean, the electrician was on site doing his first fix, running all the necessary cables. I think even Sean was surprised at the amount of cable that went into the house for the first fix. We’ve opted for LED down lighters in the kitchen, bathrooms and man cave, and standard lighting everywhere else, to try and keep the cost down a bit. We also had a meet up with the guys from Aperio Audio Visual, Craig and Chris and talked through my requirements for the home cinema set up. The set up will also include all the cabling to each TV, along with a speaker system in certain areas of the house that can be zoned. I’ll try my best to make sure this is all rigged up ready for the house warming party!
More insulation to be done, in all the roof spaces with fibreglass insulation, a horrible task, so I thought it best to delegate that part to my trusty right hand man (thanks Colin!). Because we’re having open eaves, we had to stuff the insulation into all of those gaps as well. Back up on the top floor, we finished off fixing the ply to the inside of the trusses, this acts as extra bracing, then another 50mm of Recticel insulation was fixed to that ply, ready for the plasterboard.
We ‘dry fitted’ the shower trays so we could fit the waste pipe work to each of them. We’ve just got a days work left doing all the odds and ends ready for it to be dry lined. Hopefully by the time I next write, the rain water harvesting system would’ve been delivered then that’s everything done for the first fix plumbing.
Outside the house
A good tidy up was needed out the front of the property to clear space for the ground workers to return to dig the trenches for the BT and electricity cables to be run. This required moving another few tons of stone out of the way that we’ve got remaining to build our retaining wall out the back.
The second pic (believe it or not) is the ‘after’ clean up shot. There were a few pallets of stone there before we got stuck in! Our little helper getting stuck in as well.
Once the trench was back filled we could get it looking a little bit more like a house, and get shot of some of the unsightly fencing.
The drive got it’s layer of scalpings, which made parking a lot less muddy!
The garage floor was also completed at the same time, so that’ll come in handy as bit of extra storage. It’s slowly starting to look like our home!
Next time – more work on the first fix inside for the cabling for all the TVs and the conservatory gets fitted too.
If you’re interested in building your own home, or need any advice from planning issues to renewable energy, be sure to check out http://theselfbuildsite.com
Thanks for reading – see you next time.
Dom.